NOSPI-2026-04-D2051

CompletedScheduledNGCP line

Reason / activity

1. Implementation of Wood Pole Replacement Program by contract

Details

Please be informed that the scheduled power interruption of 5LI1FAM-CMO (Famy-Comon 69kV Line) on July 11, 2026 will be deferred and for rescheduling.

Line Interrupted

5LI1FAM-CMO (Famy-Comon 69kV Line)

Affected Area

Real, Infanta and Gen. Nakar Quezon

Original Date

July 11, 2026 (Saturday) 0600H - 1800H

Revised Date

July 22, 2026 (Wednesday) 0600H - 1800H

Activities

1. Implementation of Wood Pole Replacement Program by contract

2. Preventive/corrective maintenance along the line

3. Implementation of 5-year test plan of Upper Labayat HEPP and Quezelco II - Infanta

Update on Famy-Comon 69 kV Line Maintenance and Power Interruption

Cause of Delay: A technical issue during wood pole replacement by our outsourced service provider caused multiple line troubles during re-energization. This was further compounded by a security incident at the work site when an unruly individual threatened maintenance personnel, forcing a temporary work suspension and police intervention.